Pa.qe
1. Open Meeting
2. Pledge of Allegiance
3. Approve Agenda
4. Public Hearing: Improvements to CSAH 15 5436 - 5439
(County 15/2002 Project)
Discussion on City of Mound acting as Fiscal Agent
for Councilmember Meyer's fundraiser
6. Adjourn
This is a preliminary agenda and subject to change. The Council will set a final agenda at the meeting. More current meeting
agendas may be viewed at City Hall or at the City of Mound web site: www. ciO,o_fmound, com.
IIi
Engineering
Planning
Surveying
November 12, 2002
Honorable Mayor and Members of the City Council
City of Mound
5341 Maywood Road
Mound, Minnesota 55364
SUBJECT:
City of Mound
Addendum to Feasibility Report
Improvement Project 2002 (Mound Visions 2nd)
MFRA #13646
Dear Mayor and Council Members:
As requested, we are herein submitting an Addendum to the Feasibility Report previously prepared
for the Metro Plains project's "Mound Marketplace" and "Village By the Pond". This addendum is
for the City's share of the Right-of-Way Acquisition costs of the County Road 15 project.
If you have any questions or need additional information on anything in this addendum or the
original report, we will be pleased to discuss this further with you at your convenience.
Sincerely,
MFRA
John Cameron, City Engineer
JC:rth
Enclosure
s:Xmain:Wlou 13646:\CorrespondenceXmayor-councill 1-7
-5436-
15050 23rd Avenue North · Plymouth, Minnesota · 55447
phone 763/476-6010 · fax 763/476-8532
e-mail: mfra@mfra.com
Addendum
To
And Modification of
Feasibility Report for
Improvement Project 2002
(Mound Visions 2nd)
Including Portions of County State Aid Highways 15 and 110
Street Improvements and Streetscape
(Minnesota Statutes, Chapter 429)
COUNTY 15/2002 PROJECT
RIGHT-OF- WA Y A CQ UISITION
The original Feasibility Report included only a portion of the improvement costs for the County Road
15/110 project, as they related to the "Mound Marketplace" development. For bonding purposes, it is
recommended that Mound's share of the right-of-way acquisition be consolidated with Improvement
Project 2002 (Mound Visions 2nd) and conducted as one improvement project. The total estimated cost of
ROW acquisition for the county Road 15/110 project is $4,300,000.00, of which 50 percent or
$2,150,000.00 will be the City of Mound's responsibility under its contract with Hennepin County.
The following is the estimated cost of the two projects combined (and renamed the County Road 15/2002
Project):
Improvement Project 2002
(Mound Visions 2nd)
$ 593,675.OO
Countyl 5/2002 Project
ROW Acquisition (Mound's Share)
$ 2~150,000.00
Total Estimated Cost of Two Projects combined
$ 2,743,675.00
Metro Plains Development has provided the City with a Petition and Waiver Agreement which allowed
the City to assess "Mound Marketplace" and the "Village By the Pond" an estimated project cost of
$712,657.00. This amount has been adjusted down to $593,675.00, which reflects some actual known cost
for work completed and estimated costs for future work items. This assessment will meet the 20 percent
requirement the City must meet in order to make this project feasible and allow the City to issue
improvement bonds without voter approval.
The original feasibility report also described other improvements to be made to County 15 and Highway
110 including street improvements and streetscape improvements. It is recommended that those
improvements not be constructed at this time but rather that those improvement projects be instituted as a
separate improvement project under Minnesota Statutes, Chapter 429 at a later date, most probably in the
summer or fall of 2003.
In our judgment, the consolidated County Road 15/2002 Project is necessary, feasible, cost effective and
should be made as proposed in the Feasibility Report as modified by this Addendum.
DJK-223225vl
MU195-1
-5437-
AFFIDAVIT OF MAILING IMPROVEMENT HEARING NOTICE
County of Hennepin )
City of Mound )
Bonnie Ritter, being first duly sworn, deposes and says:
I am a United States citizen, over 21 years of age, and the City Clerk of the City of
Mound, Minnesota.
On December 16, 2002, acting on behalf of said city, I deposited in the United States
post office at Mound, Minnesota, copies of the attached Notice of CSAH 15/2002
Improvements Hearing, enclosed in envelopes, with postage thereon fully prepaid,
addressed to the following persons at the addresses appearing below their respective
names:
Larry Olson
MetroPlains, Inc.
1600 University Avenue, Suite 212
St. Paul, MN 55104-3825
There is delivery service by United States mail between the place of mailing and the
places so addressed.
Bonnie Ritter, City Clerk
Subscribed and sworn to before me this lb day of ~2(-~ _~'"' ,2002.
~ublic
~~~~ c~JODI L. RAHN
Notary Publ~
Minneso~
-5438-
Notice of Public Hearing
......... ~ CSAH ~15/2002 Improvements ~ ~
NOTICE IS GIVEN that the City Council of the City of Mound, Minnesota, will meet in the
Council Chambers at 5341 Maywood Road at 12:30 p.m. on Tuesday, December 31,
2002, to consider the construction of improvements to County State Aid Highway 15
(County 15/2002 Project) from apprOximately 600' west of CSAH 110 to Cypress Lane,
consisting to the acquisition of right of way and other properties necessary for that
constructiOn pursuant to Minnesota Statutes, Chapter 429 (Act). The Project is proposed
to be constructed in conjunction with and to be combined with Improvement Project
(Mound Vision 2®) 2002 now being constructed pursuant to the Act. The estimated cost
of the County 15/2002 Project is $2,150,000.00, none of which will be specially assessed
against benefited properties. The Project consists of the City's share of the cost of a joint
construction program being undertaken by Hennepin County and the City.
Any person wishing to express an opinion about the Project will be heard orally or in
writing at the public hearing.
By Order of the City Council:
By:
Bonnie Ritter, City Clerk
Published December 21 & 28, 2002.
-5439-