CITY OF MOUND HRA/MOUND HARBOR RENAISSANCE LLC
AGENDA TOPICS FOR SEPTEMBER 3, 2002 WORKSHOP
• Master Developer Team Organization
• Land Acquisition Process
. TIF
• City Projects
o Rail Right of Way
o County 15 Re-Alignment
o Utility Re- Location
o Recovery of Costs
MOUND HARBOR RENAISSANCE, LLC
RE-DEVELOPMENT TEAM
• MASTER DEVELOPER- Mound Harbor Renaissance, Tom Stokes
• TECHNICAL-
o Engineering, Survey & Architecture- Landfrom, Steve Johnston
^ Project Manager/Civil Design- Dan Hughes
Urban Design- Carolyn Krall
^ Architecture- Ed Wilms
^ Landscape Architecture- Don Colberg
^ Planning- Kendra Lindahl
^ Survey- Mike Cannon
o Environmental- Kjolhaug Environmental Services, Mark Kjolhaug
• LEGAL-
o Permits, Soil Contamination, Wetlands, Lake Minnetonka
Conservation District, MCWD, DNR, Dredging, Grants- Dorsey &
Whitney LLP
^ Alexandra Klass
^ Jay Lindgren
o Development Agreements, Land Acquisition- Fredrikson & Byron
PA
^ Greg Munson
^ Susan Steinwall
^ David Sellergren
^ Bonnie O'Malley
o Land Acquisition- Severson, Sheldon, Dougherty & Molenda
^ Bob Bauer
• Mike Dougherty
• BROKERAGE SERVICES, SALES, MARKETING, LAND ACQUISITION-
Welsh Companies
o Brokerage- Bob Long
o Retail Leasing & Sales- Kris Schisel
o Office Leasing & Sales- Chad Anvary
• AERIAL PHOTOGRAPHY 8~ BROCHURE DESIGN- Landmark Photography
& Design
o Aerial Photography- Jim kruger
o Brochures- Jon Huelskamp
DISTRICT BY DISTRICT SUMMARY
110 South Lost Lake Auditor's Road Langdon Lake
Developer Brenmar LLC Brenshell Homes Wara Development Shaw- Lundquist
LLC, Rick & Susan
Bloom uist
Project Manager Chuck Alton Tom Stokes Chuck Alton, Rick Michael Buelow
Bloom uist
Technical Landform, Landform,. Landform, Landform,
K'olhau K'olhau K'olhau K"olhau
L al DW, SSDM, FB DW, FB DW, SSDM DW, FB
Sales & Marketing Welsh Minnetonka Realty Welsh, Susan Welsh, Shaw-
Bloom uist Lundquist
Land Acquisition Welsh Welsh Welsh Welsh
MOUND HARBOR RENAISSANCE, LLC
• LAND ACQUISITION OUTLINE
.~.
I. How?
^ City of Mound, or Mound HRA to acquire all
^ Negotiation
^ Condemnation
^ Price cap for Redeveloper reimbursement to be preset
^ City of Mound, or HRA to do very initial site preparation
^ Environmental Remediation
^ Title clearance
^ County 15 relocation
^ RR vacation
^ Redeveloper acquires from City/HRA when land is clean and title is clear.
^ All or
^ Phase by phase
^ Redeveloper completes Design and Approvals
^ During City acquisition
II. Why?
^ Condemnation threat helps -can negotiate successfully.
^ Redeveloper won't take title until clean soils.
^ Condemnation can also be used, if necessary, to clear title.
^ Huge risk for Redeveloper as to timing and up front investment.
^ If City/HRA acquire, there will always be someone who wants to develop the
assembled parcel.